1.0        Purpose     :   This procedure is to provide instruction for Store Management System.
2.0       Objective :  To Provide documented procedure of instruction for Store Management System.
3.0         Scope        :   This SOP covers the instruction for all department of store.
4.0        Responsibility   :
·   Primary      : Officer- Store
·    Secondary : In charge/Manager- Store
5.0      Procedure   :
·        General Instruction for Store:
Ø      Store the rejected/ recalled/ expiry dated material at isolated area which is fully controlled by QA department.
Ø      The sampling area should be clean and disinfected.
Ø      Store should be clean twice a day.
Ø      GRN should be made for every received material, placed in store.
Ø      The balance available at store should be calibrated as per SOP.
Ø      List of approved vendor should be available in the store.
Ø      Store should follow FIFO policy for distribution of goods in house.
·        Procedure for receiving indent from production:
Ø      Production department release the indent for raw material needed to start new batch.
Ø      Raw material store department receive the indent and review it.
Ø      Store keeper checks the previous entry of sending raw material to production.
Ø      Store personal fill the BMR sheet by entering weight of the material and AR No.
Ø      Store should entry in the log book of the given material and sends the required material to production department.
Ø      Store department should follow Good Distribution Practices.
·        Before raising the indents for material:
Ø      Consider the physical stock of the quantities already exists / ordered
Ø      Send the balance stock report to purchase department.
Ø      Purchase department finalize the purchase order after negotiations, prepare purchase order and handover to the party.
·        Procedure for Receiving the material:
Ø      After getting the intimation, receive the material at the gate house.
Ø      Check the material at gate house, as per delivery challan and quality of material i.e. damage, scratches, finishing etc.
Ø      Call to QC department for collecting the sample of raw material.
Ø      QC department should check the specification of the material and if it complies department send the Analytical Report mentioned with AR No.
Ø      After receiving analytical report which passes the material store keeper allow the goods at store.
Ø      Take the required quantity and use for it was indented.